Sunlight Projects P.Ltd. vs D.D.A. & Ors on 6 January, 2017

1. Present writ petition has been filed primarily seeking quashing of the
letter dated 9th January, 2008 issued by respondent-DDA insofar as it directs
the petitioner to pay the balance 75% premium along with interest @15%
per annum. Petitioner also prays that respondent-DDA be directed to
provide sewage, road, parking and water supply facilities at commercial Plot
No. 8, Service Centre, Sector 20, Part 2, Dwarka, Delhi.

W.P.(C) 685/2008 Page 1 of 15
2. The relevant facts of the present case are that at an auction held on
16th January, 2007 for Commercial Plot No. 8, Service Centre, Sector 20,
Part 2, Dwarka, New Delhi, petitioner was the successful bidder with the bid
of Rs. 17.51 crores. Clause 2(iii) of the auction terms and conditions states
as under:-