“a. Allow the present petition by setting aside
the impugned order dated 16.04.2016 passed by
the Ld. Sole Arbitrator Shri V K tyagi in the
arbitration proceedings between M/s JITF
Water Infrastructure Limited vs M/s Natconn
Engineering Private Limited and decide on the

OMP (T) Comm. 34/2016 Page 1/9
termination of the mandate of the Ld. Sole
Arbitrator.

b. Replace the Ld. Arbitrator by the new
arbitrator duly appointed by this Hon’ble Court
in exercise of its powers under section 14 of the
Act.