M/S K.S. Jain vs Union Of India on 24 September, 2021

1. The relief sought in the present petition before this Court is to

appointed sole Arbitrator to under Section 11(6) of the Arbitration and

Conciliation Act, 1996 to adjudicate the dispute with respondent.

2. According to petitioner, pursuant to tender rates dated 05.12.2012

submitted by the it with the respondent, the work for linking of BG Track &

Turnouts, provision of glued joint, SEJ’s, dismantling of existing track &

turnouts, handling, lifting, loading, unloading and spreading of ballast,

leading of P. Way materials and other misc. works in Motichur, Raiwala,

ARB.P. 858/2021 Page 1 of 4
Harrawala yard & shunting neck, extension in Dehradun yards in connection

with development of facilities for running 18 coach trains between Hardwar-

Dehradun section of Moradabad Division was awarded to the petitioner vide

respondent’s acceptance letter bearing No.74-N/4/1/Misc./WNMB dated

08.02.2013. The time period for completion of work was 11 months ending

on 07.01.2014.