Ite India Private Limited vs Delhi Tourism And Transportation … on 23 May, 2016

1. The appellant impugns order dated 08.02.2016, whereby the
petition under Section 9 of the Arbitration & Conciliation Act, 1996
(hereinafter referred to as “the Act”) has been dismissed.

2. By an Agreement dated 08.08.2005, the appellant was awarded
an operation contract of commercial outlets at Garden of Five Senses

FAO(OS) 46/2016 Page 1 of 23
for a period of ten years. Possession of the site was handed over to
the appellant on 23.08.2005. In terms of the agreement, contract fee
was payable and the appellant was entitled to sub-Contract outlets to
its sub-Contractors for which an NOC was issued though, it is
contended, belatedly after four years.

Source: Indian Kanoon