Gmr Kishangarh Udaipur Ahmedabad … vs National Highway Authority Of … on 29 June, 2015
1 min read1. This is a Petition filed under Section 9 of Arbitration &
Conciliation Act, 1996 (“Act” in short) seeking the following reliefs:-
PETITIONER’S CASE
2. It is the case of the petitioner that the respondent had called for
bids for design, engineering, finance, construction, operation and
maintenance of six-laning of Kishangarh – Udaipur – Ahmedabad section
of National Highway No. NH 79A, NH 79, NH 76 and NH 8. The
Petitioner was the successful bidder and was awarded the Contract. The
Concession Agreement was executed between the parties on November
30, 2011. Under the Concession Agreement, the respondent authority
had to fulfill mandatory Conditions Precedent under clause 4 and the
rights and obligations of the parties only come into effect after
fulfillment of the Conditions Precedent. It is the case of the petitioner,
that as per clause 4.1.2 of the Agreement, the respondent had to fulfill
the following obligations;
Source: Indian Kanoon