Ashwath Infratech Pvt Ltd & Anr. vs National Mission For Clean Ganga … on 24 May, 2017
1 min read1. The petitioners, by the present petition, impugn the show cause
notice dated 09.05.2017 issued by respondent no. 1, whereby the
petitioners have been directed to deploy the trash skimmers by
12.05.2017, failing which the contract awarded to the petitioners
would stand terminated.
WP(C) 4140/2017 Page 1 of 4
2. It is contended that in terms of the time period prescribed under
the contract, the petitioners were granted 36 months from the date of
deployment of equipment to complete the contract. The equipment
was to be deployed on the respondent’s location within 90 days from
the date of issuance of the letter of acceptance or within 30 days of
intimation of deployment location by respondent no. 1, whichever was
later.